> h et le> .7
00000 000000
000000
, 0
0,939. 2
a ,836,213.37
b 5100 7500 irr npv 000
3000 7400 npv L L irr S mirr S S A
A B .00
210 .54
-150 210 210 820 210 210 210 b at 10% cost o capital
c. cost of capital
d. 17% .
87000 98300 98300 select B 350000 A B Annual CF -25000000 A a. years B 0 -25000000 -25000000 8264462.80991735 b years c. d. e 0 >Sheet .7
2
,836,213.37
1
>0
Time CF 00000
2 10000000 ,300,939.42
Accept NPV>0 Accept >5% >10% >15% Accept Accept Accept 14.00% Accept MIRR >14% Accept npv Accept IRR Accept Accept )
Accept Annuity npv %
accept $478.83 B B NPV million NPV millions 1 5000000 A
B 0 -25000000 B Annual CF years A 2 10000000 0.826446281 8264462.80991735 years2
S
e
1
a
b
1
0
A
B
-1
5000000
-150
5000000
20
10
10000000
20000000
6000000
$16,108,951.52
$
18
3
4
5%
npv
$
12
$15,954,169.80
10%
$10,059,587.41
$13,897,838.42
15%
43.97%
82.03%
irr
10.8
Truck
Pulley
-17100
-22430
0.
14
5100
7500
5100 7500
5100 7500
5100 7500
14.99%
19.999%
$408.71
$3,318.11
accept both projects
14.54%
17.19%
mirr
10.10
Project S
Project
L
-10000
–
25
3000
7400
3000 7400
3000 7400
3000 7400
$814.33
$1,675.34
15.24%
14.67%
13.77%
13.46%
1.081
1.067
pi
10.13
Interest rate
NPV
NPVB
0
$1,288.00
$
820
-400
-650
10
$478.83
$372.37
-528
210
12
$366.13
$308.39
-219
14
$265.40
$
250
18
$94.46
$150.42
1100
20
$21.98
$106.96
25
($128.74)
$13.84
990
30
($244.71)
($61.56)
-325
a
20.7%
25.8%
Select
A
f
c.
$133.76
$173.70
Select B
at
17%
14.91%
17.35%
d.
mirr at 10%
18.76%
21.03%
Crossover rate
CFA-CFB
250
Below the crossover rate, select A, above the crossover rate
select B
-738
-429
-360
890
610
780
-535
14.76%
10.18
NPV
190-3
360-6
-190000
-360000
87000
98300
87000 98300
98300
98300
$11,981.99
$22,256.02
$5,161.02
$5,723.30
The value of the firm would increase by the npv.
10.12
Initial investment
–
1065000
Purchase price
900000
350000
Installation costs
165000
Initial investment 350000
1065000 350000
350000
$136,578.34
19.22%
10.21
a.
Period
Annual CF
0
-25000000
1 5000000 20000000
2 10000000 10000000
3
15000000
8000000
4 20000000 6000000
Payback
2
years
0.6666666667
2.67
1 year
0.5
Payback
1.5 years
b.
Discounted Payback
A B
Period Annual CF Annual CF
Disc Rate
Disc CF-A
Disc CF-B
1 5000000 20000000
0.9090909091
4545454.54545454
18181818.1818182
2 10000000 10000000
0.826446281
8264462.80991735
3 15000000 8000000
0.7513148009
11269722.0135237
6010518.40721262
4 20000000 6000000
0.6830134554
13660269.1073014
4098080.73219042
Discounted Payback A
24079639.3688956
3years
0.0673750005
3.067375
Discounted Payback B
1 year
0.825
1.825
A B
$12,739,908.48
$11,554,880
A and B should be selected with positive npvs
$18,243,813.02
$14,964,829
A should be selectedwith the higher npv.
$8,207,071.16
$8,643,390.4
B should be selected.
f
CFA – CFB
0
-15000000
7000000
14000000
13.53%
21.93%
20.96%
g.
2
1
1
0
Chapte
r
10
A
Uneven Cash Flow Stream
Time
CF
0
-1
5000000
1 5000000
2
10000000
3
20000000
$16,108,95
1.5
$
12
$10,059,587.
4
Accept
NPV
B
0
-150
1 20000000
3
6000000
$
18
$15,954,169.80
$13,897,838.42
b.
IRR
A
43.97%
>5%
>10%
>15%
B
82.03%
10.8
Annuity
NPV
NPV
PV of cash flows
$17,508.71
$408.71
PV of cash flows
$25,748.11
$3,318.11
IRR
14.00%
Truck
MIRR
Future value of annuity
($33,711.53)
MIRR
14.54%
>14%
Pulley
Future value of annuity
$49,575.78
MIRR
17.19%
10.10′
Project S
pv of cash flows
$10,814.33
$814.33
npv
Project L
pv of cash flows
$26,675.34
$1,675.34
Project S
15.24%
Project L
14.67%
MIRR Project S
Future value of annuity
($19,058.54)
MIRR
13.77%
MIRR Project L
Future value of annuity
($47,01
1.07
MIRR
13.46%
Profitability Index
PI
PV of cash flows/Initial investment
Project S
1.08
Project L 1.07
Project L to be selected on the basis of NPV
10.12
a.
Purchase price
900000
Installation cost
165000
1065000
PV of cash flows
$1,201,578.34
Less: Initial
$136,578.34
accept
Irr
19.
22
irr
irr>cost of capital
Reduce the cash flows by the amount of environmental costs
c.
r
NPVA
NPVB
10
$478.83
$372.37
12
$366.13
$308.39
18
$94.46
$150.42
22
($43.14)
$67.26
A
-400
-528
-219
-150
1100
820
990
-325
b.
20.65%
A
25.84%
d. MIRR
Future value of an annuity
$1,992.31
MIRR
17.35%
MIRR A
14.91%
Select B at a cost of capital of 10%
e.
Crossover rate
Year
A CF
B CF
Difference
0 -400
-650
250
-528
210
-738
-219 210
-429
-150 210
-360
1100 210
890
820 210
610
990 210
780
-325 210
-535
Crossover rate
14.76%
below the crossover rate, choose A
above the crossover rate, choose Bz
10.16.
Equivalent Annual Annuity
Plane A
Present Value of Cash Flows
$108.14
million
shorter life
$8.14
EAA
$2.26
Plane B
Equivalent Annual Annuity
$9.26
millions
longer life
EAA
$1.64
Select A
10.21
A B
Year
Annual CF
0
-25000000
2 10000000 3
15000000
4 20000000
Payback
2.6666666667
years
Year Annual CF 1.5 years
Payback B
1 20000000
2 10000000 3
8000000
4 6000000
Discounted Payback
Period
Discount Rate
Discount CF
0 -25000000 0 0
1 20000000
0.9090909091
18181818.1818182
2 10000000
0.826446281
8264462.80991735
3 8000000
0.7513148009
6010518.40721262
4 6000000
0.6830134554
4098080.73219042
Discounted Payback Payback
1.825
26446280.9917355
6818181.81818182
Period Annual CF Discount Rate Discount CF
0 -25000000 0 0 1 5000000 0.9090909091
4545454.54545454
3 15000000 0.7513148009
11269722.0135237
4 20000000 0.6830134554
13660269.1073014
24079639.3688956
920360.631104436
Disc Payback
3.067375
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read moreOur specialists are always online to help you! We are available 24/7 via live chat, WhatsApp, and phone to answer questions, correct mistakes, or just address your academic fears.
See our T&Cs